Clearing the obstacles
The concrete bridge was demolished, though precautions had to be taken because the bridge crossed a live railroad mainline, which had to be protected.
Two new bridge headers were constructed to support the new road realignment.
Safety precautions were required to protect live rail activity. The project included laying down and removing protective material on the railroad to allow for trains to pass.